This was one of our new build sites, made up of 1 block of approximately 55 units. Being adjacent to a supermarket, this was a bespoke scaffold designed to get around some tight sections. The buildings were fully scaffolded externally as well as each floor being fully birdcaged.
We also devised our own unique method of scaffold erection which allowed the site to utilise all of the advantages that come with using porotherm blocks. The complicated roof created some challenges, along with the link between the buildings which had to be erected last. We then had to dismantle the remainder of the scaffold without any crane, making the job more laborious than usual. However, despite all of these challenges, we completed this site successfully.